SWAN Newsletter #11
February 27, 2007
LOWER PAXTON TOWNSHIP
AUTHORITY BOARD MEETING
Attended by Bill Oakland and Shelly Kunkel. Reported
by Shelly Kunkel.
Aside from the formalities and a decision to levy a $15 fee per settlement for establishing new account ownership (!) when RE is transferred by sale within the township, the following were the highlights:
1.
An easement agreement has
been brokered with the Vartan Group to secure a sewer easement at the
Oakhurst interceptor. The fee paid by LP to Vartan for the easement was
$131,625.
2.
In Devon Manor, a ÒResearch
and DevelopmentÓ project is ongoing whereby LP is replacing sewer traps and
sump pumps in selected homes. 2 have been completed and a 3rd
is being negotiated. LP had previously identified that approx. 20 homes
in Devon Manor each were contributing 3,000 gallons /house I&I during flood
times, with 10 homes being the worst offenders. Discussion was held about
keeping the townships costs as low as possible for the work.
3.
Paxton Creek update Ð There
was lengthy discussion about the status of the 2007 June deadline for LP to
satisfy their DEP consent order. LP must come up with a proposed solution
to the I&I problems and has been considering 3 options: Reaching
agreement with Harrisburg to pass more flow down to the city for treatment,
storage of LPÕs overflow somewhere within the township, and treatment within
the township. The latter option has been tagged by CET engineering as the
most expensive. Previously LP and Susquehanna had been working in tandem
on this goal b/c the sewer flows from LP to Susquehanna and then on to the City
of Harrisburg. In a series of events called ÒbizarreÓ by the CET
engineer in attendance (discussion of newspaper article), Susquehanna has
elected to pursue an independent parallel inquiry about their sewer options
with another engineering firm (HRG/Bob Grubic). Susquehanna will now
independently commission a 537 Plan to determine their options, just as
Lower Paxton is doing with its own engineers. Ideally, HRG will present
Susquehanna with the same options that LP has already determined to be
available. And HRG may even suggest the Commerce Park site to Susquehanna
Authority as the optimal place to locate a storage facility. If
Susquehanna is given the same answer from their engineers as LP has been given,
hopes are high that the Commerce Park solution will prevail. (LP is
further advanced in this process b/c they have been working under a June 07
deadline for several years, Susquehanna will have to Òget up to speed on the
issues.Ó). Discussion among Authority members indicates that the
Susquehanna Authority board members are
sympathetic to the LP issues and the preference to Òwork togetherÓ, however
there is a political overlay with the Susq. Commissioners that cannot be
ignored. LP Authority consensus was Susq.Commissioners will be
politically able to endorse/embrace a joint venture if HRG comes back with the
same findings as CET has for LP. A duplicate report (albeit at duplicate
costs to taxpayers) would take the politicians off the hook for an unpopular
decision.
4.
Alternately, if Susquehanna
and LP engineers differ on their recommendations, then LP is faced with a Ògo
it aloneÓ strategy. Discussion was had about the wisdom of the $600,000
purchase of the lot in Commerce Park, and Norm Hoffer opined that it is a good
investment and that the township will not regret the purchase. That
purchase was intended to accommodate I&I for BOTH townships. IF LP
pursues an independent solution, less land would be necessary for the
project. Bill Weaver, Authority Manager, suggested the township look at
the last remaining lot in Commerce Park Ð opposite Kunkel driveway Ð as a
possible site for the LP only storage facility.
5.
With the June 07 deadline
looming, DEP has indicated that it will accept a Òplan of intentÓ from LP in
June Ð and DEP will hold off on the approval process, giving an additional 90
days for SusquehannaÕs 537 Plan to be completed. So it appears that the
June deadline is soft.
6.
Randy Hearst (?), Esq. has
been retained as Òspecial counselÓ to assist Steve Stine in the Lower Paxton
Creek issue.
7.
LP is arranging a meeting
with Lee MacDonald (?) of the Hbg. Sewer Authority Ð to be preceded by a letter
drafted by CET engineering and signed by Bill Hawk arguing the complexities of
sewer flow from LP through Susquehanna to the City.
Next Authority meeting is on 4/27.
March 6, 2007
LOWER PAXTON TOWNSHIP
BOARD OF SUPERVISORS
(7:40 -7:55 PM)
Reported & attended by Ted Robertson.
Under the Manager's report, George Wolfe announced that
breakfast with the Easter Bunny would take place Saturday, March 31, 2007.
Reservations are required. On Saturday, April 7, 2007, the Easter egg hunt and
extravaganza will take place at 1:00 PM. Call Parks & Recreation for
details.
Under old business, five appointments were made to the
Parks & Recreation Board.
Under new business, the preliminary/final subdivision plan
for 1525 Blue Mountain Parkway was approved unanimously. This involved four
lots on 10.29 acres. The Planning Module for 4000 Linglestown Road, Autumn
View, which involves 18 town homes, was approved unanimously.
David Blain announced that all but one of the 70+/-
entities involved with the Capital Tax collection had filed to have the Bureau
explain the apparent deficiency in distributions in taxes collected by the
Bureau.
March 8, 2007
LOWER PAXTON TOWNSHIP PUBLIC SAFETY COMMITTEE MEETING (7:00 -8:05 PM)
Reported and attended by Ted Robertson.
Under old business much of the discussion concerned the
approval of the Capital Funding Plan Phase III. This was discussed in an
earlier Township Supervisor's meeting. It was interesting to note that from the
time of approval by the Supervisors until the vehicles will be put in service
will be 18 months to 2 years.
The March 13 workshop meeting will be delayed in order to
allow more time for preparation.
The discussion of fire apparatus access roads raised
some interesting points. This involves any road, cul-de-sac, turnaround, or
dead end primarily in developments, and other than main thoro-fares. There are
specifications in the national fire code concerning the above. It became
obvious, during this discussion that the fire-chiefs were not happy with the
variances granted by Staff and the Planning Commission over their objections to
violations of the code specifications proposed by the developers/builders. It
was felt, by those attending, that the Supervisors would "rubber
stamp" any variances proposed by the Staff and Planning Commission.
Another point that needs clarification: When, in the
process of a project development, is the Public Safety Committee supposed to
see the plans for the project? Is there anything in the Township Code that
defines this? I raised this question in a Public Safety Committee meeting
almost a year ago, and didn't receive a clear answer. In fact, one of the fire
chiefs has stopped submitting comments to Staff because he felt they were being
ignored.
In my opinion, the above issue requires the following:
1.) A clear definition of responsibility for actions at definite
time frames during the course of development of a project.
2.) If any objections are raised with respect to code
or township ordinances, those objections should be made
a matter of record. And the reasons for granting variances over these objections
should also be made a matter of record.
3.) I believe the national fire code also requires
that a certified fire department official must sign off on
every development plan.
4.) This further strengthens the need for a
professional planner in the township.
March 13, 2007
LOWER PAXTON
TOWNSHIP SUPERVISORS WORKSHOP MEETING
(7:30 - 9:35 PM)
Attended by Watson Fisher, Mark Levine &
Ted Robertson. Reported by Ted Robertson.
Much of the workshop session involved various items under
the jurisdiction of Parks and Recreation. Supervisor Bill Hornung suggested at
an earlier meeting that the township try to get local participation in the
development of the skate board facility in George Park. The goal is to have 1/2
of the total funds ($250,000) be provided by the public. This project should be
successful as a result of an excellent presentation on the part of those
involved.
Another item of interest suggested by the Arts Council, was
the creation of an LP Twp variety band. The retired director of the C.D. High
School Band has expressed an interest in leading such an endeavor.
Under Item 5, it was suggested that the property at 6500
Union Deposit Road (19 acres), zoned AR under the new zoning ordinance be
covered by a green space overlay. The present Act 537 sanitary sewer plan does
not allow for sanitary sewer on land zoned AR. An amendment to Act 537 would
have to be submitted. The Supervisors seemed somewhat agreeable to this idea
since the sewer system is in the adjacent development.
Under Item 7 the Paxtonia area was suggested as a possible
area for the Business Improvements District. This would extend eastward from
Route 22, Old Jonestown Road split roughly to Mountain
Road.
March 14, 2007
LOWER PAXTON TOWNSHIP
PLANNING COMMISSION MEETING
(7:00 - 9:20 PM)
Attended by Eric Epstein, Watson
Fisher, Mark Levine, Loren Barisch, Ben Chotiner, Eileen Hurley, Betty Miller,
Darwin Aurand & Ted Robertson. Reported by Ted Robertson.
The Planning Commission approved
the preliminary subdivision and land development plan for Stray Winds Farm at
the previously agreed to 449 units, with all the other conditions SWAN
negotiated with Triple Crown Corporation. Eric Epstein thanked the
representatives of Triple Crown for their good faith efforts in arriving at a
development plan believed to be in the best interests for all parties.
The rezoning request for Lawrence
C. Conjar's property at 6500 Union Deposit Road was approved by a 4-3
vote. Some details of this property are covered in the previous Supervisors
Workshop session of March 13, 2007. The plan would include 18 units on 19+
acres. Mark Levine indicated to the Planning Commission that the Supervisors
were somewhat favorable to the green space overlay to the AR zoning with an
amendment to the Act 537 sanitary sewer plan.
The preliminary/final subdivision
plan #06-46 was approved unanimously for this same property. This was simply a
request to join the two lots presently making up this property into one.
The final subdivision plan 07-03
for phase 2 of Chelsey Falls was approved with two additional lots acquired
since the preliminary plan was approved.
The resubmission of the
preliminary/final land development plan 07-04 was approved. This resubmission
was made necessary by the developer/builder's failure to respond within the
15-day time limit from the initial approval of the plan.
March 14, 2007
LOWER PAXTON TOWNSHIP
PLANNING COMMISSION MEETING
Attended by Eric Epstein, Ted
Robertson, Mark Levine, Eileen Hurley, Darwin Aurand, Betty Miller,
Ben Chotiner, Loren Barisch and Watson Fisher. Reported by Watson Fisher.
GREENWAY COMMTTEE REPORT - Mr. Chris Johnson gave a brief update on the continuing
activities of the townshipÕs Greenway Committee. Mr. Johnson reported that the
committee and the consultants are working together to develop a Master Plan to
guide the township in the creation of a network of green spaces and hiking and
biking trails. The plan will identify existing corridors that could become
trails, green spaces that can be preserved, and other opportunities for
recreational spaces in the township. It will also address possible new township
ordinances that could assist in the creation of these facilities. The plan is
intended to be realistic in its scope and to recognize the need to minimize any
impact on private property. It will become a guide for planning groups
including the Planning Commission in the creation and preservation of green
spaces as development continues in the township. The next public meeting on
this project is scheduled for 7:30 PM, Tuesday April 3, 2007, at the township
building.
STRAY WINDS FARM - Preliminary Subdivision & Land development Plan
#06-42 This project was
presented and tabled at the January commission meeting. The site for this
project encompasses the large open area surrounding the intersection of Crums
Mill Road and McIntosh Road. It contains 243 acres in Lower Paxton Township
zoned R-C Residential Cluster and has been approved for 449 housing units. With
the addition of the portion in Susquehanna Township it contains 303 acres and
is planned to have 523 housing units. There is a legal challenge to the Zoning
Hearing BoardÕs approval of 449 units in Lower Paxton Township and that legal
matter remains unresolved. Any township action on this plan is of course contingent
on the successful resolution of the legal action.
Engineer Bob Fisher reported that
the staff, HRG, and county comments have been or are being addressed and
resolved. Staff engineer Jim Snyder said he recommended approval of the ten
waivers that were requested by the developer. Mr. Fisher noted that the project
will be reviewed by the Susquehanna Township officials at their meeting in
April. SWANÕs chairman Eric Epstein spoke to thank Triple Crown, the developer,
for their cooperation with SWAN over the course of the design process in order
to incorporate a variety of significant plan changes and improvements that had
been suggested including open space, buffers, and road improvements.
Plans for Crums Mill Road and
McIntosh Road, which traverse the development, were discussed. Mr. Fisher
stated that because of the existing slopes of the shoulders and the proximity
of trees to the roads it would be difficult to widen them more than a few feet
on each side. They will be reconfiguring the dangerous intersection of Crums
Mill and McIntosh and correcting the oververtical condition on Crums Mill Road
as well as revamping the intersection at McIntosh and Colonial Roads. The need
to widen Paxton Church Road was also mentioned.
The commission requested that
curbing be installed at the Crums Mill McIntosh Road intersection and at the
new intersections in the development to better define them for safety reasons.
It was agreed that planting areas would be allowed in cul-de-sacs and at
entrance drives if their maintenance was clearly stated to be the
responsibility of a homeownersÕ association. The suggestion was made that now
is the time to consider the incorporation of greenway trails in the development
before the planning process gets too far along.
The commission recommended
approval of this plan including the ten waiver requests and all the comments
but is contingent upon the resolution of the outstanding legal appeal.
LAWRENCE W. CONJAR - Rezoning Request. This request was to rezone two
adjacent parcels of land totaling 19 acres at 6500 Union Deposit Road from AR
Agricultural Residential to Open Space Overly District. The plan, with the
requested rezoning, is for 18 half-acre residential lots with the balance of
the acreage remaining open space owned by a homeownersÕ association. This plan
would result in the preservation of much of the existing woodlands. The overlay
district would require the lots to be served by public sewers involving an
amendment to the Act 537 plan. Without this rezoning the resultant plan would
consist of approximately 7 large building lots with on site sewerage treatment.
SWANÕs Mark Levine spoke in favor of the zoning change stating that the
supervisors indicated a preference for sewer connections over on site sewage
disposal. The builder reviewed the parcelÕs history, it having been previously
zoned R-1 and it being adjacent to a development zoned R-1. It is the desire of
the owner to maintain the wooded areas as much as possible.
The commission by a 4-3 vote
recommended approval of the zoning change subject to the necessary amendment to
Act 537 and a legally enforceable provision to preserve the unused woodlands in
common ownership.
LAWRENCE W. CONJAR - Preliminary/Final Subdivision Plan #06-46 With the recommended approval of the
above zoning request for the two adjacent parcels at 6500 Union Deposit Road,
this submission is to combine the two properties into a single parcel totaling
19 acres. The applicant had no objections to the staff, HRG, and county
comments. The waiver request to eliminate the requirement for sidewalks and
curbs was amended to require curbing along Union Deposit Road.
The commission recommended
approval of the lot consolidation plan subject to the comments.
TNP CARWASH - Preliminary/Final Land Development Plan #07-02 This project is located on a 2
acre lot at the intersection of Briarsdale Road and Peiffers Lane which is
zoned CG General Commercial. All comments had been received but there had not
been enough time for the engineer to review them in detail. As a result the
plan was tabled until next monthÕs meeting.
CHELSEY FALLS, PHASE 2 - Final Subdivision plan #07-03 This project consists of 19
single family dwellings on a 14.5 acre tract on the south side of Goose Valley
Road at the intersection of Fairway Lane. There are 6 waiver requests and these
were approved at the time of the preliminary submission. Concern was raised for
an existing storm water problem and a dangerous drop off along the road near
this intersection, both of which remain from the Phase 1 construction of this
development.
The commission recommended
approval of this submission contingent upon the resolution of the remaining
Phase 1 issues.
4800 LINGLESTOWN ROAD - Preliminary/Final Land Development Plan #07-04 This project for a new 2 story
office building on a 4.3 acre site on the north side of Linglestown Road was
approved by the Planning Commission at their December 13, 2006 meeting. After
notification of the approval the applicant did not acknowledge same within the
required 15 days necessitating this resubmission.
The commission recommended
approval of this resubmission.
March 20, 2007
LOWER PAXTON TOWNSHIP
BOARD OF SUPERVISORS MEETING
(7:30 -8:20 PM)
Attended by Watson Fisher &
Ted Robertson. Reported by Ted Robertson. (Chairman Hawke was absent.)
Under old business, a letter of
understanding between the Township and the Freedom Group for the development of
a skate park in Thomas B. George Park was approved unanimously. Details of this
project were covered in the report on the prior workshop meeting of March 13,
2007.
Under new business contracts for
cleaning services at the Municipal Center, the Friendship Center, and the
Public Works & Sewer operations buildings were approved.
The preliminary/final subdivision
plan for Russell J. Cluk Enterprises was approved unanimously. This involves 4
lots on 18.1 acres south of Commerce Drive and west of Crums Mill Road. This is
zoned business campus under the new zoning ordinance. No immediate development
is anticipated.
The preliminary/final land
development plan for additions and renovations to the Dauphin County Technical
School was approved unanimously. It was stated that an increase of only 25
students is expected since only one new program is being added. There was a
concern expressed about increased traffic on Locust Lane and the intersection
at Fairmount Drive and Nyes Road.
The preliminary/final land
development plan for 4800 Linglestown Road was approved unanimously. This
project was covered in the report on the Planning Commission Meeting of March
14, 2007.
The preliminary/final land
development for 5710 Union Deposit Road was approved unanimously. This involves
8 lots on 4.68 acres north of Union Deposit Road.
The planning module for the Blue
Mountain Parkway subdivision plan was approved unanimously.
March 22, 2007
LOWER PAXTON TOWNSHIP
ZONING HEARING BOARD
(7:00 -8:45 PM)
Attended and reported by Ted
Robertson.
Docket #1227 - The application for
a free standing sign by Members 1st Federal Credit Union at 1021 Briarsdale
Road (South of Union Deposit Road, near Route 83) was denied. The requested
sign exceeded the height specified for this commercially zoned district. The no
vote was unanimous.
Docket #1228 - The variance
request for the freestanding sign for Hartman Motorcars was tabled for a future
meeting. The variance request for the directional signs and the wall signs was
approved.
March 26, 2007
SUSQUEHANNA WATER GAP
COALITION MEETING
Attended
and reported by Darwin Aurand.
Background: The Susquehanna Water Gap Coalition is
a newly organized group of local residents and affected environmental groups
that have mutual interest in local development activities, and in protecting
the natural resources of the Susquehanna River Gap (parameters yet to be
defined). Since this group has
only met twice, has no incorporation status or officers; the group is
attempting to establish goals and related mission statement and objectives as
part of their agenda. At present
it is a loose confederation of people with like minded environmental objectives
that seem willing to help others as they deal with development activities
absent a formal organization structure.
March 26, 2007 Meeting:
Two individuals, Paul Zeph (DEP),
and Cliff Dillman have voluntarily agreed to Òco-chairÓ meetings until such
time as the group becomes more formally organized. While many meeting participants have affiliations with such
groups as Audubon, Sierra, and DEP, these individuals were not officially
representing these organizations.
Debra Bowman, who provided the group with status on many development
related activities, officially represented the Central Pennsylvania
Conservancy. Also present were
several individuals representing Cove Mountain Partnership (similar SWAN
interests), Cindy Stein of the Paxton Creek Watershed, Penn Twp. Zoning Hearing
Board, Marysville Boro Planning Board, Keystone Trails Assn., and the
Susquehanna Trails Assn. There was
also individual representation from Greg Burgdorf, a professional
geologist. My list might not be
all-inclusive since many individuals were attending their first meeting.
Meeting participants: Cliff Dillman, Paul Zeph, David Ertel,
Ben Reed, Michael and Donna Lomma, Debra Bowman, Greg Burgdorf, Brian Foster,
Darwin Aurand, Cindy Stein, and others not yet published in the meeting
minutes.
Pinpointed areas of Focus:
through
DEP & DCNR to assess Cove Mtn. hydrology)
impacts
Informal objectives/working goals
(these are not in any prioritized order):
1.
One of the key objectives for
the group will be environmental advocacy and education.
2.
Some participants have had
some experience in activists roles, and it was discussed that ideas to help
influence development approaches could/would be discussed to develop strategy.
3.
Various liaison outreach
groups could be contacted to provide communications with external environmental
organizations and groups.
4.
Endeavor to try to upgrade
local ordinances
5.
Protection of natural
resources, rivers, and valley lands localized to the Susquehanna River within
Dauphin County (precise scope not yet defined)
6.
Serve as a clearinghouse and
network for developments and other threats
7.
Unite or coordinate groupsÕ
efforts to protect or save key environment
8.
Help citizens take
appropriate action to protect resources of the Susquehanna Gap.
Overall, this is a group of very
interested and environmentally active participants that has not yet gotten
structured and organized, but are very committed to trying to develop some
strategies and resources to help review and oversee local development.
Next meeting tentatively scheduled
for April 23, 2007, 6 p.m.
March 27, 2007
LOWER PAXTON TOWNSHIP BOARD OF SUPERVISORS/PLANNING COMMISSION WORKSHOP MEETING
(5:30 - 7:50 PM)
Attended and reported by Ted
Robertson.
The Greenway Committee gave a
brief review of the current status of the work of the group. The last public
meeting will be held April 3, 2007. The committee expects a final draft of the
plans to be presented to the Supervisors in late June.
Under old business, amendments to
the new zoning ordinance and to the new zoning maps were discussed. Since the
Supervisors, and members of the Planning Commission, and the
developers/builders involved were the only ones having copies of those
amendments making it to his point, members of the public (SWAN) could offer no
input at this stage.
The same was true of the proposed
subdivision and land development ordinance (SALDO). After pointed questions by
the public in attendance, Mr. Wolfe assured everyone that once a final draft is
agreed to, copies of the final draft will be made available to the public,
hopefully before the mandated 30 day notice is printed in the local newspaper.
Another meeting concerning SALDO is planned for April 24, 2007 at 5:30 PM.
The Supervisors requested the Planning Commission to look into the need for the designation of business improvement districts within the Township. The Planning Commission agreed to do this.
SWAN will have to be on the
lookout for any public notification concerning the above subject.